Published 31 marzo 2022
The recent decision in Cubex (UK) Limited v Balfour Beatty Group Limited [2021] EWHC 3445 (TCC) is an example of when the Court will refuse to enforce an Adjudicator’s Award. A key factor in this decision was the type of works being carried out and whether these were in fact “construction operations”.
In around September 2021 Cubex (UK) Limited (Cubex) made an application for summary judgement to enforce an adjudication award of approximately £400,000 plus interest. In the adjudication, Cubex had contended – and the adjudicator agreed – that Balfour Beatty Group Limited (BB), by contracting with a third party for the design and supply of doors for use in fit-out works at Woolwich Station, had committed a repudiatory breach of the contract it had concluded with Cubex.
BB raised the following defences to summary judgment:
1. It had real prospects of showing that:
a. The contract(s) related in whole or in part to “excluded operations” under the Construction Act, so the adjudicator had no jurisdiction over the dispute; and/or
b. Cubex purported to refer / the adjudicator purported to decide more than one dispute and/or the single contract contended for by Cubex never came into existence, so the adjudicator had no jurisdiction; and/or
c. By deciding the critically important issue of contract formation on a basis which neither party had advanced / been able to make submissions in relation to or put forward evidence on, the adjudicator acted in breach of the principles of natural justice; and
2. Cubex’s delay (of approximately three years) in bringing proceedings was a “compelling reason” for refusing summary judgment.
The judge refused Cubex’s application for three main reasons, namely:
1. The alleged contract did not relate to “construction operations” under the Construction Act; whilst it did encompass design, such design related to the supply of doors (an “excluded operation” under section 105(2) of the Construction Act) and not to “construction operations”, as required by the Act.2. The contract found by the adjudicator never came into existence and so he was not properly appointed under a contract about which there could be no dispute.
3. The adjudicator had failed to draw his contract analysis to the parties’ attention, which was sufficient to constitute a material breach of the rules of natural justice e.g. to ensure that each party is fully appraised of any arguments against it (whether raised by its opponent or the adjudicator) and is given a reasonable opportunity to comment. By the decision not reflecting arguments advanced by either party, the adjudicator had arguably gone off “on a frolic of his own”.
The delay in bringing proceedings was not considered a compelling reason to refuse the application; there is no obligation to make an application on any specific date within the relevant limitation period and the lateness did not give rise to any abuse of process.
London - Walbrook
+44 (0) 207 894 6309
By Peter Allchorne, Emma Fuller
By Will Potts, Daniel Hobson
By Lucy Harris, David Knapp, Marlon Ellis
By Stefan Desbordes
By Rachel Rough, Kathryn Nisbet
By Helen Mason
By Jonathan Deverill
By Richard Stallard
By Peter Allchorne, Michael McCabe
By Peter Allchorne, Caroline Hall, Michael McCabe
By Richard Rowe
By Claire Laver, Rhys Pousette, Jemma Lewis, Caroline Bigos
By Emma Fuller, Joanna Folan
By William Swift
By Toby Vallance
By Joanne Waters