In 2013 the Government launched its Construction 2025 Industry Strategy to provide a vision for "long-term strategic action by government and industry to continue to work together to promote the success of the UK construction sector". Building Information Modelling (BIM) was high on the agenda.
It identifies BIM as critical to allow the sector to deliver more sustainable buildings more quickly and more efficiently. The Government is keen to put the UK at the forefront of BIM and by 2016, all centrally procured government construction projects must be delivered using BIM. This will apply throughout the supply chain across all values of project. However, in Consultant NBS' recent survey 95% of respondents were aware of BIM, but only 54% were actually using it. There could be a number of reasons for this relatively mixed take up; lack of knowledge, lack of opportunity, lack of technical skill or lack of resource. An understanding of the contractual framework for the implementation of BIM is an important first step to removing any "blockers" to the successful implementation of BIM construction projects.
"At its simplest level, BIM provides a common environment for all information defining building, facility or asset together with its common parts and activities. This includes building shape, design and construction time, costs, physical performance, logistics and more".
BIM is used at a number of different levels of maturity from Level 0 being a paper based process with CAD drawings to Level 3 which is a fully integrated and collaborative process on a web-enabled hub. For 2016, the Government target is Level 2 BIM, in which separate disciplines create their own models, but all project data is shared electronically in a common environment. In its Construction 2025 Strategy the Government is expecting the UK Government and industry to move to Level 3 BIM between 2013 and 2025.
The contractual framework for Level 2 BIM has been established. Level 3 BIM presents a different set of contractual challenges which are not addressed in this article.
The Government's BIM Strategy followed the recommendations of the BIM Industry Working Group, which recognised that contractual issues had the potential to act as a source of inertia holding back the adoption of BIM on projects. The Working Party report dated March 2011 recommended little change to the "fundamental building blocks" of existing contracts to facilitate working at Level 2 BIM.
The Working Party recommended the use of simple amendments to existing standard form contracts, to incorporate standard BIM Protocols and Service Schedules to define BIM specific roles; ways of working and desired outputs.
The Construction Industry Council's ("CIC") response to the Government's BIM Strategy was to issue a CIC/BIM Protocol for use on all common construction contracts to support Level 2 BIM.
The CIC Protocol makes minimum changes to pre-existing contractual arrangements and sets out the parties obligations to provide defined elements of their works/services using models. The Protocol is a contractual document and takes precedence over existing contracts.
The CIC also sponsored the production of PAS1192-2:2013, by the British Standards Institution, which is a specification for the information management requirements necessary for working at BIM Level 2.
The CIC/BIM Protocol should be read in conjunction with PAS1192-2:2013.
All parties engaged in a project using BIM are required to have a Protocol appended to their contracts. This will ensure common standards and methods of working. It is the responsibility of the "Employer" in each contract in the supply chain to ensure that a Protocol is appended to the contract.
The Protocol includes a 'model' amendment to expressly incorporate the Protocol into standard forms of contract.
The MPDT is a key contractual document annexed to the Protocol (Appendix 1). It defines which models are covered by the Protocol, it allocates responsibility for the preparation of the models and identifies the Level of Detail ("LOD") required at project stages or "data drops".
Definitions of LOD's can be found in PAS 1192-2. The project stages or "data drops" should match the stages used on building and infrastructure projects, or professional appointments, such as RIBA Plan of Work.
The IR is the second key contractual document annexed to the Protocol (Appendix 2). The IR contains the information necessary for the production and development of the models in a consistent and uniform way across the project. For example it will prescribe the Common Data Environment, the software details, the file formats, file layers, the language, abbreviations and symbols, zoning requirements and information protocols such as spatial co-ordination and information exchange. Most of the Information in the IR will be taken from the tender documents, such as the Employer's Information Requirements.
It is the responsibility of the "Information Manager" to agree and issue the IR, which should be incorporated into all contracts on the Project.
The Protocol requires the Employer to appoint an Information Manager. It is expected that this role will form part of a wider set of duties, and is likely to be performed by the Design Lead. However, it could be a stand alone appointment if the Employer choses to.
The scope of services for the Information Manager needs to be properly defined in the Appointment.
The CIC have published a Scope of Services document for the role of Information Manager.
Those services include:
The Information Manager has no design related duties.
The Information Manager is in effect the "policeman" for the Information Model.
As a consequence of the increased collaboration necessary when working on a project using BIM, the issue of intellectual property rights is specifically addressed in the Protocol.
The ownership of rights in the models produced by a Project Team member remain vested in that Team Member.
However the Employer is granted a non-exclusive licence to use the material in the models for the "Permitted Purpose"; which is defined as; "a purpose related to the Project (or the construction, operation and maintenance of the Project) which is consistent with the applicable Level of Detail of the relevant Model and the purpose for which the relevant Model was prepared".
The licence also permits the Employer to grant sub-licences on identical terms to other Project Team Members. The licence does not include the right to change any information in the Model without the Project Team Member's consent, except in limited circumstances. So, in short, the Intellectual Property rights in the information Modelling remain with the originator, but the Employer and the other Project Team Members have the benefit of licences to use that information for "the Permitted Purpose".
The Protocol requires the Employer to ensure a Protocol is incorporated into all Project Agreements that the IR and MPDT are reviewed and updated at relevant stages and that an Information Manager is appointed at all times.
The Project Team Members are required to produce the specified Models to the required Level of Detail specified in the MPDT, using the level of skill and care required under the original contract, at the stage(s) specified in and in accordance with the IR.
In terms of liability for the Information Modelling, the Protocol states that a Project Team Member shall have no liability for the use of, copying of, amendment of or modification of such information other than as permitted by the licence to use for the "Permitted Purpose".
Similarly the Employer's liability for any Information Modelling provided to the Project Team Members is limited to that in respect of the licence it granted for use for the "Permitted Purpose".
The contractual framework for operating at BIM Level 2 is available, via the CIC/BIM Protocol, supplemented by PAS1192-2, and existing standard form contracts.
These are standard form documents. Amendments to these documents could create increased liability and contractual uncertainty.
The effectiveness of these contract documents is assisted by careful comprehensive and informed preparation of the technical data which supports them, the MPDT and the IR.
Leeds
+44 (0)113 251 4888
By Mark Roach
By Nick Hillyard, Kai von Pahlen, Leon R Smith
By Sophie Engel, Ben Daniels
By Rebecca Austin
By Jilly Petrie
By Duncan Strachan, Francesca Muscutt, Emily Webber
By Fiona Gill, Rebecca Austin
By Mark Roach, Morgan Raines
By Emma Milham
By Mark Roach, Chris Lewis
By Mark Roach, Lauren Howe
By Harriet Hawkins
By Warren Kemp, Harriet Hawkins
By Mark Roach, Harriet Hawkins